Koziakov & Partners | View firm profile
Koziakov & Partners advised the respondent, the construction company, in commercial litigation against a state authority, who acted as the claimant. The claim concerned an unreasonable delay in completing the project, resulting in a substantial fine under the contract. The legal strategy, arguments and evidence introduced by our legal team were of great assistance to the client during the litigation. Following consideration of the dispute by the court of first instance and the appeal court, the penalty for the delay initially claimed by the claimant was substantially reduced, saving the client more than UAH 10 million.
Our team advises various construction companies on infrastructure project implementation, contractual procedures, and post-contractual disputes.