A full bench of the Gauteng High Court has delivered a significant judgment clarifying when courts may dismiss claims for prolonged inactivity. The ruling establishes that unexplained delays of several years, even without malicious intent, can constitute an abuse of process and result in dismissal. This decision reinforces the duty of plaintiffs to actively prosecute their claims and keep defendants informed of progress.

South AfricaLitigation, Mediation & Arbitration

On 16 October 2026, a full bench of the Gauteng Division of the High Court, Johannesburg, delivered judgment in an appeal concerning the dismissal of an action for want of prosecution. The judgment usefully restates the principles that apply when a plaintiff has allowed a claim to lie dormant for an extended period and confirms that such a delay may result in the claim being dismissed. Significantly, the Court held that an inordinate and unexplained delay may in itself constitute an abuse of process, regardless of the plaintiff’s intentions.

In TUHF Ltd v Sasria SOC Limited, the Court dismissed an appeal against an order of the High Court (the Court a quo) dismissing TUHF’s action against Sasria on the basis that TUHF had inexcusably delayed in prosecuting it.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from