In the case of Reliance Infrastructure Limited v. Shanghai Electric Group Co., Ltd. [2024] SGHC(I) 3, the Singapore International Commercial Court...

ChinaLitigation, Mediation & Arbitration

Abstract

In the case of Reliance Infrastructure Limited v. Shanghai Electric Group Co., Ltd. [2024] SGHC(I) 3, the Singapore International Commercial Court ("SICC") dismissed Reliance Infrastructure Limited ("Reliance Infra")'s application for revocation of an arbitral award. Reliance Infra had argued, inter alia, that (a) the Singapore International Arbitration Centre ("SIAC") lacked jurisdiction' (b) the award had been procured by fraud; and (c) the award was in any event contrary to the public policy of Singapore. In the challenged award, the tribunal had ordered Reliance Infra to pay Shanghai Electric approximately US$146 million. 

The principal question in this case was whether Reliance Infra, by not alleging forgery in the signature of the arbitration agreement during the arbitration proceedings, was deemed to have waived its right to object to the arbitral tribunal's jurisdiction on that ground.