ARTICLE · 14 APRIL 2026

Landowners Not Always Promoters: Supreme Court Adopts ‘Control Test’ In Real Estate Projects

The Supreme Court’s decision in Sriganesh Chandrasekaran & Ors. v. M/s Unishire Homes LLP & Ors. (2026 INSC 172) marks a significant development in determining the liability of landowners in real estate projects.

IndiaReal Estate and Construction

INTRODUCTION

The Supreme Court’s decision in Sriganesh Chandrasekaran & Ors. v. M/s Unishire Homes LLP & Ors. (2026 INSC 172) marks a significant development in determining the liability of landowners in real estate projects. The judgment clarifies when landowners can be treated as promoters or principals, particularly in cases involving delay in possession and deficiency in service.

The ruling reinforces a key principle: liability in real estate projects follows actual control and contractual responsibility, not mere ownership of land.

FACTUAL MATRIX

The dispute arose from a Joint Development Agreement (JDA) between landowners and a developer, under which the developer undertook construction and sale of residential units. The developer failed to deliver possession within the stipulated timeline, leading to consumer complaints alleging deficiency in service. The National Consumer Disputes Redressal Commission (NCDRC) initially imposed liability solely on the developer.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from