ARTICLE · 27 NOVEMBER 2026

NHAI Extends Cost Escalation Compensation Mechanism For Bitumen Price Increases

India's National Highways Authority has extended its cost escalation compensation mechanism to help highway contractors manage the financial impact of persistently high bitumen prices. The extension applies to specific project types executed during 2026, though eligibility depends on when bids were originally submitted. This policy aims to provide relief to construction and maintenance projects facing material cost pressures.

IndiaReal Estate and Construction

The National Highways Authority of India (NHAI), vide Policy Circular bearing reference no. 18.141/2026 dated October 20, 2026, has circulated the Ministry of Road Transport and Highways’ (MoRTH) decision to extend the Cost Escalation Compensation Mechanism for National Highway projects undertaken under the Engineering, Procurement and Construction (EPC), Hybrid Annuity Model (HAM), Performance-Based Maintenance Contract (PBMC) and maintenance contract modes. The mechanism seeks to mitigate the impact of significant increases in bitumen prices on highway construction and maintenance projects.

In view of the continued high prices of bitumen, MoRTH, vide Circular No. NH-24028/03/2026-H dated October 8, 2026, has extended the validity of the mechanism until December 31, 2026. The extension is subject to two conditions: the relevant works must have been executed between April 1, 2026, and December 31, 2026, and the bid due date for the project must have been prior to April 1, 2026.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from