ARTICLE · 01 SEPTEMBER 2017

D.C. Circuit Vacates And Remands FERC Approval Of Southeast Market Pipelines Project

Hogan Lovells Cadwalader
Hogan Lovells Cadwalader
Contributor
Hogan Lovells Cadwalader

Hogan Lovells Cadwalader

Hogan Lovells Cadwalader is a global law firm trusted by clients to deliver on complex, high-stakes...

View firm profile
Explore more from Hogan Lovells Cadwalader

On Tuesday, August 22, 2017, the U.S. Court of Appeals for the District of Columbia Circuit vacated and remanded an order by the Federal Energy Regulatory Commission ("FERC") authorizing the construction and operation of the ...

United StatesEnergy and Natural Resources

On Tuesday, August 22, 2017, the U.S. Court of Appeals for the District of Columbia Circuit vacated and remanded an order by the Federal Energy Regulatory Commission (“FERC”) authorizing the construction and operation of the Southeast Market Pipelines Project (the “Certificate Order”).1  Although the court rejected several of the claims raised by environmental and landowner groups seeking judicial review of the Certificate Order, a divided panel held that FERC’s environmental review of the project failed to adequately consider the downstream effects of greenhouse gas emissions resulting from increased power generation.  In reaching this conclusion, the court distinguished this case from three 2016 D.C. Circuit decisions upholding FERC’s National Environmental Policy Act (“NEPA”) review of liquefied natural gas (“LNG”) facilities2—finding that whereas FERC is not the “legally relevant cause” and thus not required to review the indirect effects of increased natural gas