On June 28, 2016, the U.S. Court of Appeals for the District of Columbia Circuit rejected two related challenges to the Federal Energy Regulatory Commission's environmental review of the Sabine Pass LNG and Freeport LNG...

United StatesEnergy and Natural Resources

On June 28, 2016, the U.S. Court of Appeals for the District of Columbia Circuit rejected two related challenges to the Federal Energy Regulatory Commission's environmental review of the Sabine Pass LNG and Freeport LNG applications to site, construct, and operate liquefied natural gas ("LNG") export facilities under Section 3 of the Natural Gas Act. 

The first decision, Sierra Club v. FERC, No. 14-1249 (the "Sabine Pass Decision") addressed a challenge to FERC's 2014 order amending the maximum production capacity of Sabine Pass LNG's existing LNG export facilities, which were initially approved in a separate 2012 proceeding.  The second decision, Sierra Club and Galveston Baykeeper v. FERC, No. 14-1275 (the "Freeport LNG Decision"), involved FERC's order approving Freeport LNG's application to add export and liquefaction facilities to its existing import terminals.