On Nov. 18, 2026, the New York Department of Public Service (DPS) Staff released its white paper in Case 26-E-0335, the Nuclear Reliability Backbone proceeding of the Public Service Commission (Commission). The paper sets out Staff’s recommendations on how New York should pursue a cost-effective path to new, advanced nuclear generation. It builds on the stakeholder comments and an Oct. 5, 2026, technical conference that DPS Staff convened under the Commission’s June 11, 2026, order.
Background: New York’s 8.4 GW Nuclear Reliability Backbone and NYPA’s 1 GW Project
In her 2026 State of the State address, Gov. Kathy Hochul called for a Nuclear Reliability Backbone and directed the Commission to facilitate a cost-effective pathway to 4 GW of new advanced nuclear energy. That followed her June 2025 directive to the New York Power Authority (NYPA) to develop and construct a separate advanced nuclear plant of at least 1 GW in upstate New York. Together, the two initiatives total 5 GW of