ARTICLE · 18 NOVEMBER 2011

Clarity At Last On Judicial Review Time Limits

Boyes Turner
Boyes Turner
Contributor
Boyes Turner

Boyes Turner

Located in the Thames Valley, Boyes Turner is a regional UK law firm with an impressive...

View firm profile
Explore more from Boyes Turner

Judicial review of planning decisions will probably not be at the forefront of most developers’ minds at the moment as permissions themselves are at historically low levels and so there is simply less scope for aggrieved residents or others to make applications for review of decisions.

United KingdomReal Estate and Construction
Peter Daniel
Peter Daniel

Judicial review of planning decisions will probably not be at the forefront of most developers' minds at the moment as permissions themselves are at historically low levels and so there is simply less scope for aggrieved residents or others to make applications for review of decisions.

When development picks up again as it surely will developers can be heartened by the recent decision in the case of Macrae v Herefordshire District Council which if it remains un-appealed will bring some certainty to what has been a very confused topic.

Planners and developers will be aware that after the struggle to obtain planning permission there is one more potential hurdle to be overcome before a developer can exercise an option or declare a contract unconditional and go ahead and buy a site which they have bought subject to planning. That hurdle is [a] potential review by the Courts of the planning authority's decision.