Contract Out Of Concurrent Confusion

Dispute arises where one of those causes is the result of the employer's action or omission and the other is the result of the contractor's.

United KingdomReal Estate and Construction

Following the Court of Appeal's decision last week in North Midland Building Limited v Cyden Homes Limited, regarding contract provisions dealing with concurrent delay, we thought it would be helpful to briefly summarise the position.

A useful working definition of concurrent delay, which Coulson LJ, giving the leading judgement in North Midland, "gratefully adopts" was that given in Adyard Abu Dhabi v SD Marine Services.  In Adyard, Hamblen J said that a concurrent delay is:

"a period of project overrun which is caused by two or more effective causes of delay which are of approximately equal causative potency."

Dispute arises where one of those causes is the result of the employer's action or omission and the other is the result of the contractor's.  The conundrum is, in such circumstances which party should bear the cost of the delay, the employer or the contractor?