As we have discussed in previous issues of IQ and our Annual Review, under the FIDIC form there is a requirement on both the Contractor and Employer to submit notices about claims ..

United KingdomReal Estate and Construction

As we have discussed in previous issues of IQ and our Annual Review, under the FIDIC form there is a requirement on both the Contractor1 and Employer2 to submit notices about claims and that if they do not do so within the timescales set out in the contract there is a real chance that they will lose the right to make such a claim.

This issue came up in the recent English case of Commercial Management (Investments) Ltd v Mitchell Design and Construct Ltd & Anr.3  In April 2002 Regorco had entered into a subcontract with Mitchell to carry out certain ground treatment (or vibro-compaction) works at a site on which a warehouse was to be built. By a separate subcontract Regorco also agreed to carry out the piling at the site.  The vibro-compaction works were carried out at the end of March 2002, and the piling was installed a month or two later. Practical completion of the building was achieved on 19 December 2002. However, some nine years later, in November 2011, the