Proceeding Regularly And Diligently And The "Hurry-Up" Notice

Fenwick Elliott LLP
Fenwick Elliott LLP
Contributor
Fenwick Elliott LLP

Fenwick Elliott LLP

Fenwick Elliott provides a comprehensive range of legal services on every aspect of the...

View firm profile
Explore more from Fenwick Elliott LLP

The recent case of Leander Construction Ltd v Mulalley & Co Ltd [2011] EWHC 3449 (TCC), helps to clarify the law in relation to implied terms requiring a party to proceed regularly and diligently.

United KingdomReal Estate and Construction

The recent case of Leander Construction Ltd v Mulalley & Co Ltd [2011] EWHC 3449 (TCC), helps to clarify the law in relation to implied terms requiring a party to proceed regularly and diligently.

The Facts:

In September 2010, Mulalley (the main contractor) engaged Leander (the sub-contractor) to carry out groundworks, drainage, the concrete framework and other associated works at a development known as Tigers Head in Lewisham. By May 2011 it was clear that the sub-contract works were delayed - each party blamed the other. Mulalley served two withholding notices as a result of the alleged delays, claiming that Leander had failed to carry out the sub-contract works in accordance with the programme dates and period set out in the Activity Schedule. Ultimately, Leander commenced proceedings in the Technology and Construction Court.