The Building Safety Act 2022, together with related secondary legislation, mandates that works to a higher risk building which require building control approval must go through the Building Safety Regulator’s ‘gateway’ process.

United KingdomReal Estate and Construction

The Building Safety Act 2022, together with related secondary legislation, mandates that works to a higher risk building which require building control approval must go through the Building Safety Regulator’s ‘gateway’ process.

There are three gateways which operate as follows:

  • Gateway 1 – introduces new requirements into the planning system to ensure that fire safety is properly considered at the planning application stage.

  • Gateway 2 – forms part of the building control approval process, before construction works begin. It acts as a strict ‘hold point,’ with construction unable to lawfully commence before the Building Safety Regulator (BSR) issues the Gateway 2 approval.

  • Gateway 3 – occurs at completion of the construction works, when the BSR assesses whether the work has been carried out and completed in accordance with the Building Regulations.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from