As Ahmed Ibrahim discusses, multi-tiered dispute
resolution clauses are a common feature of construction contracts.
These clauses require the parties to exhaust one or more stages of
alternative dispute resolution mechanisms before they are permitted
to invoke the "ultimate" dispute resolution process,
generally arbitration or litigation. The typical pre-arbitration
(or litigation) steps called for include a period of amicable
settlement, referral to a committee comprising the senior
management of both parties, and adjudication before independent
third parties which may be binding or non-binding.
Commonly used forms in the Middle East
Perhaps the best-known international examples of multi-tiered
dispute resolution clauses are clause 67 of the FIDIC 1987 Red Book
and clause 20 of its 1999 Rainbow Suite of Contracts, both of which
are familiar to arbitrators and other legal practitioners in the
MENA region being the most commonly used standard forms in that
region1.