The Bombay Court in its decision in M/s Krishna Constructions & Ors vs. Mr. Subhash Uttam Dalvi & Ors 1, held that once the entire project is placed before the flat takers at the time of the agreement, then the promoter is not required to obtain prior consent of the flat takers as long as the builder puts up additional construction in accordance with the layout plan, building rules and Development Control Regulations.

FACTS:

The Appellants have challenged the interim order passed by the Trial Court in an Interim Application preferred in a suit filed by Respondent No. 1 wherein the Appellants are arrayed as Defendant Nos. 1 to 3.

Respondent No. 1 (original Plaintiff) is a purchaser of Flat No. 502, admeasuring 67.11 Sq. mtrs, 5th floor ("suit flat") in the building, Lotus Court ("said building") developed by the Appellants.