Delhi High Court Quashes NOC Requirement For Further Construction

Kochhar & Co.
Kochhar & Co.
Contributor
Kochhar & Co.

Kochhar & Co.

Kochhar & Co has one of the largest full service commercial law practices in Bangalore. The firm...

View firm profile
Explore more from Kochhar & Co.

An analysis of the judgment in Harish Bajaj & Anr. versus North Delhi Municipal Corporation & Anr. - wherein the Hon'ble Delhi High Court held that the NOC requirement of the NDMC from all the owners in a building was unwarranted.

IndiaReal Estate and Construction

An analysis of Delhi High Court's judgment in Harish Bajaj & Anr. versus North Delhi Municipal Corporation & Anr. - wherein the Hon'ble Delhi High Court held that the NOC requirement of the North Delhi Municipal Corporation (NDMC) from all the owners in a building was unwarranted.

Background & facts:

The Hon'ble Delhi High Court while hearing an appeal from an aggrieved resident of Prashant Vihar has quashed the NDMC's requirement for obtaining a No-Objection Certificate (NOC) from the other occupants of a building while undertaking further construction as permitted under the MPD – 2021.

The acting Chief Justice and Justice Anu Malhotra took into consideration the history of events and the factual matrix of the dispute of this case. They heard the respondents (North Delhi Municipal Corporation) who placed reliance on S. 347 (B) (f) of the Delhi Municipal Corporation Act, 1957 claiming that it was a statutory requirement for the Appellants to furnish