Share on LinkedInShare on LinkedIn

ARTICLE · 11 MAY 2022

The Importance Of Following The Contractual Dispute Resolution Mechanism Before Arbitration: Devanshi Construction v. Central Public Works Department, Region Bhopal

Tuli & Co
Tuli & Co
Contributor
Tuli & Co

Tuli & Co

About us: Tuli & Co was established in 2000 to service the Indian and international insurance and...

View firm profile
Explore more from Tuli & Co

The Chhattisgarh High Court has held that a claimant must exhaust any contractually specified dispute resolution mechanism leading up to arbitration before seeking a reference to arbitration.

IndiaLitigation, Mediation & Arbitration

The Chhattisgarh High Court has held that a claimant must exhaust any contractually specified dispute resolution mechanism leading up to arbitration before seeking a reference to arbitration. 

Brief Facts

Devanshi Construction and the Central Public Works Department ("CPWD") entered into an agreement for the construction of a boundary wall around the CRPF Battalion Camp in Chhattisgarh. A dispute arose between the parties relating to the non-payment of various amounts for work done under the agreement.

Devanshi referred the matter to arbitration but the CPWD refused to agree to a nominee and Devanshi approached the High Court for the appointment of an arbitrator.

Arguments before the Chhattisgarh High Court