Contractual Clarity Over Context: Delhi High Court Reaffirms The Limits Of Interpretation

In a recent decision, the Division Bench of the Delhi High Court in Oil and Natural Gas Corporation Ltd. v. JSIW Infrastructure Pvt. Ltd. has clarified the scope of contractual interpretation and reaffirmed the limited yet crucial role of courts under the Arbitration and Conciliation Act, 1996.

IndiaLitigation, Mediation & Arbitration

In a recent decision, the Division Bench of the Delhi High Court in Oil and Natural Gas Corporation Ltd. (ONGC) v. JSIW Infrastructure Pvt. Ltd. [FAO(OS)(COMM) 59/2024 & 60/2024] has clarified the scope of contractual interpretation and reaffirmed the limited yet crucial role of courts under the Arbitration and Conciliation Act, 1996 ("the Act"). The judgment underscores that where the terms of a contract are clear and unambiguous, external aids such as pre-contractual correspondence cannot be relied upon to reinterpret or rewrite the agreed terms.

Background of the Dispute

The dispute arose out of a lump sum contract awarded to JSIW Infrastructure Pvt. Ltd. by ONGC for a pipeline replacement project. While JSIW had bid unconditionally, an issue cropped up regarding the reimbursement of duties specifically, Countervailing Duty (CVD), as the required pipes were to be imported due to unavailability of the same in India.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from