ARTICLE · 08 JULY 2022

Another Decision On The Importance Of Following The Contractual Dispute Resolution Mechanism Before Arbitration: (Sobha Ltd V Nava Vishwa Shashi Vijaya & Ors

Tuli & Co
Tuli & Co
Contributor
Tuli & Co

Tuli & Co

About us: Tuli & Co was established in 2000 to service the Indian and international insurance and...

View firm profile
Explore more from Tuli & Co

Following our summary of the Chhattisgarh High Court decision in Devanshi Construction v. Central Public Works Department, Region Bhopal,

IndiaLitigation, Mediation & Arbitration

Another decision on The Importance of Following the Contractual Dispute Resolution Mechanism Before Arbitration: (Sobha Ltd v Nava Vishwa Shashi Vijaya & Ors)1

Following our summary of the Chhattisgarh High Court decision in Devanshi Construction v. Central Public Works Department, Region Bhopal, the Karnataka High Court has also held that when the parties have contractually agreed to a dispute resolution mechanism, then this must be followed before arbitration is invoked.

Facts

The defendant issued a work order for construction work in favour of the plaintiff, who completed the construction work and handed over possession to the defendant. However, the defendant failed to pay the balance amounts due despite repeated requests.