INTRODUCTION
The Hon'ble National Company Law Appellate Tribunal,New
Delhi, in its recent judgment in Ahluwalia Contracts
(India) Limited v. Raheja Developers
Limited1 dated July 23, 2019, held that
insolvency plea cannot be rejected if the disputed claim is not
raised prior to the demand notice under Section 8 of the Insolvency
and Bankruptcy Code, 2016.
FACTS
The Appellant in the aforesaid case i.e.
Ahluwalia Contracts (India) Limited, filed an application under
Section 9 of the Insolvency and Bankruptcy Code, 2016 against the
Raheja Developers Limited (Respondent). The
Adjudicating Authority (National Company Law
Tribunal, New Delhi), by an impugned order dated September 19,
2018, rejected the application on the ground that the claim of the
Appallent falls within the ambit of 'disputed
claim'.