The following is a snapshot of the important orders passed by the National Company Law Appellate Tribunal ("NCLAT"), under the Insolvency and Bankruptcy Code...

IndiaInsolvency/Bankruptcy/Re-Structuring

The following is a snapshot of the important orders passed by the National Company Law Appellate Tribunal ("NCLAT"), under the Insolvency and Bankruptcy Code, 2016 ("Code"), during the period between February 16, 2025 to February 28, 2025.

For ease of reference, the orders have been categorized and dealt with in the following categories i.e., Pre-admission stage, Corporate Insolvency Resolution Process ("CIRP") stage, Post CIRP stage, Liquidation and Miscellaneous.

A. Pre-admission Stage

1. In Adhunik Corporation Limited v.Shivam India Limited (Company Appeal (AT) (Insolvency) No. 1427 of 2023), the question before the NCLAT was whether refundable financial assistance given towards operationalization of the corporate debtor's factory would qualify as financial debt, in absence of a stipulation regarding the payment of interest. While answering the query in affirmative, the NCLAT observed that for a debt to be considered a 'financial debt' under Section 5(8)

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from