The following is a snapshot of the important orders passed by the National Company Law Appellate Tribunal ("NCLAT"), under the Insolvency and Bankruptcy Code, 2016 ("Code"), during the period between...

IndiaInsolvency/Bankruptcy/Re-Structuring

The following is a snapshot of the important orders passed by the National Company Law Appellate Tribunal ("NCLAT"), under the Insolvency and Bankruptcy Code, 2016 ("Code"), during the period between October 1, 2023 to October 15, 2023. For ease of reference, the orders have been categorized and dealt with in the following categories i.e., Pre-admission stage, Corporate Insolvency Resolution Process ("CIRP") stage, Liquidation stage, and Miscellaneous.

PRE-ADMISSION STAGE

  1. In Suresh Khola v. Abdulhadi Almailem Trading Company W.L.L (Comp. App. (AT) (Ins) No. 1063 of 2023 & I.A. No. 3673, 3674, 4537 of 2023), the NCLAT held that where the goods supplied were defective, a Section 9 application to recover the amount paid towards such defective goods is non-maintainable as a claim of damages does not fall within the purview of 'debt.'

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from