Share on LinkedInShare on LinkedIn

ARTICLE · 21 AUGUST 2019

A Dispute Must Exist Prior To Issuance Of Demand Notice Under §8(1) Of The Insolvency And Bankruptcy Code

Tuli & Co
Tuli & Co
Contributor
Tuli & Co

Tuli & Co

About us: Tuli & Co was established in 2000 to service the Indian and international insurance and...

View firm profile
Explore more from Tuli & Co

Given this judgment, corporate debtors will now need to be prompt in raising any disputes they have pertaining to claims made on them by Operational Creditors.

IndiaInsolvency/Bankruptcy/Re-Structuring

Introduction

The National Company Law Appellate Tribunal ("NCLAT") in its recent judgment in Ahluwalia Contracts (India) Ltd v Raheja Developers Ltd has held that an application under §9 of the Insolvency and Bankruptcy Code 2016 ("I&B Code") can only be rejected if the dispute in relation to the claim pre-exists the date of receipt of demand notice or invoice issued under §8 of the I&B Code.

Facts

Ahluwalia Contracts (India) Ltd ("Operational Creditor") entered into agreements with Raheja Developers Ltd ("Corporate Debtor") for construction and plumbing works at Gurgaon, Haryana. The Operational Creditor served a demand notice dated 28 April 2018 under §8 of the I&B Code for unpaid invoices amounting to c. ₹3.37 Crores in respect of works performed for the Corporate Debtor.