The Importance Of Time Limits In Shipbuilding Contracts – Seller’s Action Time-Barred Due To Failure To Institute Arbitration Proceedings Timeously

A Shipbuilding Contract typically provides for arbitration instead of litigation as its dispute resolution mechanism.

ChinaTransport

Background

A Shipbuilding Contract typically provides for arbitration instead of litigation as its dispute resolution mechanism. Further, in the event the Buyer cancels or terminates the Shipbuilding Contract, there is usually also a contractual timeframe within which the Seller is required to institute arbitration proceedings in order to dispute the Buyer's cancellation and/or termination of the said Contract.

In Nanjing Tianshun Shipbuilding Co. Ltd, Jiangsu Skyrun International Group Co. Ltd v Orchard Tankers Pte Ltd [2011] EWHC 164 (Comm), Justice David Steel was asked to consider whether failure by the Seller to institute arbitration proceedings to dispute the Buyer's cancellation and/or termination of the Shipbuilding Contract within the time period stipulated in the Contract barred the Seller from subsequently commencing litigation in this regard.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from