ARTICLE · 29 JULY 2026

Interest On Costs In Expropriation Cases Run From Date Of Order: Ontario Divisional Court, City Of Ottawa v. MacEwen Petroleum Inc., 2025 ONSC 6955

This website uses cookies to enhance user experience, monitor site usage, and manage traffic analytics. By continuing to browse, visitors consent to the cookie policy detailed in the site's privacy documentation.

CanadaPrivacy

The Ontario Divisional Court recently considered whether an expropriation claimant is entitled to interest on legal costs from a date prior to the Tribunal’s costs order in City of Ottawa v. MacEwen Petroleum Inc., 2025 ONSC 6955.

The appeal arose from the City of Ottawa’s expropriation of lands required for a segment of its rail transit line – lands of which MacEwen Petroleum Inc. (“MacEwen”) was a lessee. The City and MacEwen settled MacEwen’s compensation claims under the Expropriations Act, R.S.O. 1990, c. E.26 ( the “Act”), leaving only the issue of costs to be determined by the Ontario Land Tribunal (the “Tribunal”). 

The Tribunal awarded MacEwen costs and ordered that interest on those costs run from the date MacEwen delivered its bill of costs to the City, reasoning that such an award was consistent with the principle that claimants in expropriation proceedings should be fully indemnified and made economically whole. 

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.