In contract litigation, damages provisions often do more work than parties expect—and sometimes less than litigants later claim. The First Department’s decision in Gamma USA, Inc. v. Pavarini McGovern, LLC is a useful reminder that courts will read damages limitations by their actual scope, not by their perceived practical effect.
Background: The Contract Framework
Gamma USA, Inc., a subcontractor on a major hotel, retail, and theater renovation project in Times Square, commenced an action to recover damages from Pavarini McGovern, LLC for failure to release contractual retainage owed. Pavarini McGovern counterclaimed, alleging that Gamma’s breaches caused the project owner, Times Square Hotel Owner LLC, to incur substantial additional costs (Gamma USA, Inc v Pavarini McGovern, LLC, 2026 NY Slip Op 05237 [Sup Ct, NY Cnty, Sept. 10, 2026]). Under the Construction Management Agreement between the owner and Pavarini McGovern, delay damages were liquidated at $10,000 per day, capped at