The Arizona Court of Appeals recently denied a contractor's
claim that the owner had violated Arizona's prompt pay act
("Prompt Pay") despite the owner's admission that it
had not paid the contractor or objected to the payment application
within the statutory time.1 The court's reason for
denying the claim? The payment application included items not
supplied within "the preceding thirty day billing
cycle."2 That's it.
The contractor explained that imposing a strict thirty-day
billing cycle would up-end the usual dealings between contractors
and subcontractors and create problematic situations regarding
materials that are often acquired, stored, and installed during
different billing cycles.3 The court did not
disagree, but stated that such a potential impact made no
difference to its ruling. Instead, it noted that if a statute's
"plain language" "results in awkward procedures, or
leads to a harsh result" (as it seemed to acknowledge happened
here)4, it is up to the