Business Interruption: Coverage For Period Of Delayed Resumption Resulting From Post-Rupture Pipeline Investigation

Jones Day
Jones Day
Contributor
Jones Day

Jones Day

Jones Day is a global law firm with more than 2,400 lawyers in 40 offices across five continents....

View firm profile
Explore more from Jones Day

A peril causes covered property damage and business interruption, and also triggers legal obligations to respond to government orders that increase the cost and length of time that would have been required simply to rebuild the property as it was at the time of the peril.

United StatesInsurance

A peril causes covered property damage and business interruption, and also triggers legal obligations to respond to government orders that increase the cost and length of time that would have been required simply to rebuild the property as it was at the time of the peril.  This is common when government regulators order (and common sense dictates) that measures be taken to minimize the likelihood that the incident will recur.  Whether coverage exists for the increased costs to repair or replace insured property, and for the increased time element losses, is a frequent dispute arising in claims for property damage and business interruption losses.

A federal trial court recently addressed some of these issues in Lion Oil Co. v. National Union Fire Ins. Co .of Pittsburgh, PA., Civ. No. 13-CV-1071 (W.D Ark., El Dorado Div., Sept. 10, 2015).  Policyholder Lion Oil Company ("Lion") owns a refinery in Arkansas which receives oil from a 200-mile long pipeline owned and