New York Legislature Passes Data Center Moratorium; Bill Awaits Governor’s Approval

Greenberg Traurig
Greenberg Traurig
Contributor
Greenberg Traurig

Greenberg Traurig

Greenberg Traurig, LLP has approximately 3,200 lawyers across 51 locations in the United States,...

View firm profile
Explore more from Greenberg Traurig

New York's legislature has passed the Responsible Data Center Development Act, which would fundamentally transform how large data centers are regulated, financed, and operated in the state. The bill establishes a one-year moratorium on new permits, mandates that data centers bear full infrastructure costs without shifting expenses to ratepayers, and imposes aggressive renewable energy requirements reaching 90% by 2040.

United StatesEnvironment

In the final days of the legislative session, both the New York Senate and Assembly passed the Responsible Data Center Development Act, A11560/S10642. The bill will not become law unless signed by Gov. Kathy Hochul. If she signs the bill, it would reshape data center development in New York — and could influence policy nationwide. 

Targeted One-Year Moratorium 

The bill imposes a one-year moratorium on the issuance of permits and approvals by the Department of Environmental Conservation (DEC) for new large data centers (≥20 MW). 

Importantly, the moratorium is not a blanket freeze. It does not apply to: 

  • Projects that have commenced construction,
  • Renewals, modifications, or reissuances of existing permits and approvals, or

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from