On Feb. 12, 2026, the New York State Public Service Commission (PSC) initiated a new proceeding (Case 26-E-0045) to reform how large electricity users connect to the grid. Case 26-E-0045...

United StatesEnergy and Natural Resources

On Feb. 12, 2026, the New York State Public Service Commission (PSC) initiated a new proceeding (Case 26-E-0045) to reform how large electricity users connect to the grid. Case 26-E-0045, titled "In the Matter to Address Interconnection Reforms for Large Loads," aims to reform and define interconnection policies for high-demand electric customers and support both modernization and economic development goals. This proceeding follows the Governor's direction in her State of the State address to attract responsible new businesses, give them the certainty they need to invest in New York, and protect New York ratepayers.

What Is This Proceeding About?

At its core, Case 26-E-0045 is a PSC effort to consider changes to the rules governing interconnection — the technical and administrative process by which large electricity users physically and contractually connect to the grid. This is significant because traditional interconnection policies in New York have, until

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from