ARTICLE · 14 MAY 2024

Delays In Renewable Energy Siting In New York: A Closer Look At State Audit Findings

Greenberg Traurig
Greenberg Traurig
Contributor
Greenberg Traurig

Greenberg Traurig

Greenberg Traurig, LLP has approximately 3,200 lawyers across 51 locations in the United States,...

View firm profile
Explore more from Greenberg Traurig

On April 24, 2024, New York State Comptroller Thomas DiNapoli released an audit report on the Office of Renewable Energy Siting (ORES), which was established...

United StatesEnergy and Natural Resources

On April 24, 2024, New York State Comptroller Thomas DiNapoli released an audit report on the Office of Renewable Energy Siting (ORES), which was established under the Climate Leadership and Community Protection Act (CLCPA) to accelerate the siting of large-scale renewable energy projects. The key finding of the report, that the siting process from application submission to the issuance of siting permits averaged about 1,333 days–nearly 3.7 years–will come as no surprise to those who are working to get renewable energy projects approved and constructed in New York state. The audit covers the period from April 2020 through July 2023 and aims to evaluate ORES's effectiveness in achieving New York's ambitious renewable energy targets. The findings are particularly relevant given that the New York legislature just expanded the ORES portfolio to include transmission permitting for renewable energy projects.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from