ARTICLE · 15 APRIL 2025

On Capital Allowances - UK Supreme Court Narrows Scope Of "Expenditure On The Provision Of Plant" In Orsted West Of Duddon Sands

Travers Smith LLP
Travers Smith LLP
Contributor
Travers Smith LLP

Travers Smith LLP

It is not just law at Travers Smith. We treat our clients’ business as our business, their dispute...

View firm profile
Explore more from Travers Smith LLP

The UK Supreme Court has ruled that costs incurred on environmental surveys and studies during the planning stages of offshore windfarms do not qualify for capital allowances...

United KingdomTax

On 15 April 2026, the Supreme Court unanimously ruled that costs incurred by Ørsted (a global offshore energy company) on environmental surveys and studies conducted during the planning stages of its offshore windfarms did not qualify for capital allowances.

What has happened?

The Court held that the statutory requirement for expenditure to be "on the provision of" plant demands a close connection between the money spent and the plant itself. Costs of pre-construction surveys and studies — however necessary they may have been to the overall project — fell well outside that boundary.

Businesses involved in large-scale infrastructure projects cannot assume that all capital costs incurred in connection with the building plant will qualify for UK capital allowances. The statutory test is narrow, and the Court has confirmed it should stay that way.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.