On 15 April 2026, the Supreme Court unanimously ruled that costs incurred by Ørsted (a global offshore energy company) on environmental surveys and studies conducted during the planning stages of its offshore windfarms did not qualify for capital allowances.
What has happened?
The Court held that the statutory requirement for expenditure to be "on the provision of" plant demands a close connection between the money spent and the plant itself. Costs of pre-construction surveys and studies — however necessary they may have been to the overall project — fell well outside that boundary.
Businesses involved in large-scale infrastructure projects cannot assume that all capital costs incurred in connection with the building plant will qualify for UK capital allowances. The statutory test is narrow, and the Court has confirmed it should stay that way.