Will The Grant Of An Extension Of Time Always Prevent An Employer From Deducting Liquidated Or Delay Damages?

Fenwick Elliott LLP
Fenwick Elliott LLP
Contributor
Fenwick Elliott LLP

Fenwick Elliott LLP

Fenwick Elliott provides a comprehensive range of legal services on every aspect of the...

View firm profile
Explore more from Fenwick Elliott LLP

In our article headed "What constitutes unreasonable and vexatious behaviour when a notice of determination is served?", we discussed the case of Reinwood Limited v Brown & Sons Limited, where HHJ Gilliland QC having summarised the existing authorities, set out six propositions to assist in deciding whether a notice has been given "unreasonably or vexatiously."

United KingdomReal Estate and Construction

In our article headed "What constitutes unreasonable and vexatious behaviour when a notice of determination is served?", we discussed the case of Reinwood Limited v Brown & Sons Limited, where HHJ Gilliland QC having summarised the existing authorities, set out six propositions to assist in deciding whether a notice has been given "unreasonably or vexatiously." For details of these, please click here.

The case has now come before the Court of Appeal, where the decision at first instance has been overturned, although no comment was made on the propositions referred to above. Indeed as can sometimes be the way with appeals, the court looked at the case in a different way and ultimately decided that if the conditions for the deduction of liquidated and ascertained damages ("LAD’s") from a payment certificate were satisfied at the time when the employer gave notice of its intention to deduct, then even if the relevant certificate of non-completion was cancelled by a subsequent grant of