Will a Warranty Always Enable an Employer to Pursue a Claim Against the Contractor if the Developer Becomes Insolvent?

Fenwick Elliott LLP
Fenwick Elliott LLP
Contributor
Fenwick Elliott LLP

Fenwick Elliott LLP

Fenwick Elliott provides a comprehensive range of legal services on every aspect of the...

View firm profile
Explore more from Fenwick Elliott LLP

Chelverton Properties Ltd, property developers, entered into a contract with Safeway under which Chelverton were to design and construct a supermarket which included a two-deck car park.

United KingdomReal Estate and Construction

Chelverton Properties Ltd, property developers, entered into a contract with Safeway under which Chelverton were to design and construct a supermarket which included a two-deck car park. Chelverton entered into a building contract with Interserve. Interserve entered into a warranty with Safeway and Chelverton. A dispute arose about the surface of the car park. Chelverton and Interserve entered into a compromise agreement. Chelverton then became insolvent and Safeway having carried out remedial works, sought to recover the costs of those remedial works under the warranty from Interserve. Clause 3.3 of the warranty provided as follows:-

"The Contractor shall owe no duties or have any liability under this deed which are greater or of longer duration in that which it owes to the Developer under the Building Contract."