In short, the overall dispute concerned a biomass energy plant in North Wales that was never built.

United KingdomReal Estate and Construction

My colleague Jesse Way has written separately about the termination issues that arose in the case of PBS Energo AS v Bester Generacion UK Ltd & Anr;1 the case also considered the meaning of "unforeseeable ground conditions" and the judgment includes a useful summary of the position making reference to previous caselaw such as the Obrascon decision.

In short, the overall dispute concerned a biomass energy plant in North Wales that was never built. The contract was an amended version of the FIDIC Silver Book 1999 for EPC or turnkey projects and one of the many disagreements related to who was responsible for the risk of the asbestos which was found under the surface and which had to be removed to get planning permission finalised.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.