In MT Højgaard A/S v E.ON Climate &
Renewables UK Robin Rigg East Ltd and others [2017] UKSC 59,
the court considered the two standards of duty generally applied to
design & build contractors: the obligation to use reasonable
skill and care in relation to design, and the obligation to design
a product that is fit for its intended purpose. In what is a
landmark decision, the Supreme Court has held, reinstating the
first instance judgment, that the contractor was liable under the
fitness for purpose ("FFP") obligation, despite the
contractor not being negligent, and therefore not in breach of the
reasonable skill and care clause found elsewhere in the
contract.
This is an extremely important decision. It will have
significant ramifications for contractors and, to a lesser extent,
consultants who may now find themselves liable under similar
warranties/contractual promises. Depending on the precise terms of
cover this may leave insureds unable to recover losses under