The case of Redwing Construction -v- Charles Wishart [2010] is
about the enforcement of an adjudicator's decision. There are
two key issues:
- Had a dispute decided in the second adjudication already been
determined in the first adjudication?
- Did the second adjudicator's correction to his decision go
beyond the constraints of the slip rule? If the slip rule could be
used, had it been applied within a reasonable time?
Background
Wishart engaged Redwing to carry out a refurbishment of a
residential property in London. The form of contract was a JCT
Prime Cost Building Contract (2006 Revision 1 with amendments). The
contract fee was £3,500 per week and the estimated prime cost
was £723,334.64. Redwing took possession of the site on 14
July 2008. Completion was scheduled to take place on 12 December
2008. As you would usually expect, a number of variations were
ordered so an extension of time was granted until 31 January 2009.
Wishart took partial possession in