Share on LinkedInShare on LinkedIn

ARTICLE · 29 JUNE 2011

The TCC Considers The Slip Rule: A Useful Reminder…

The case of Redwing Construction –v- Charles Wishart [2010] is about the enforcement of an adjudicator’s decision.

United KingdomReal Estate and Construction
Rebecca Evans
Rebecca Evans

The case of Redwing Construction -v- Charles Wishart [2010] is about the enforcement of an adjudicator's decision. There are two key issues:

  1. Had a dispute decided in the second adjudication already been determined in the first adjudication?
  2. Did the second adjudicator's correction to his decision go beyond the constraints of the slip rule? If the slip rule could be used, had it been applied within a reasonable time?

Background

Wishart engaged Redwing to carry out a refurbishment of a residential property in London. The form of contract was a JCT Prime Cost Building Contract (2006 Revision 1 with amendments). The contract fee was £3,500 per week and the estimated prime cost was £723,334.64. Redwing took possession of the site on 14 July 2008. Completion was scheduled to take place on 12 December 2008. As you would usually expect, a number of variations were ordered so an extension of time was granted until 31 January 2009. Wishart took partial possession in

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from