The recent Technology and Construction Court judgment in the
case of Mears Limited v Costplan Services (South East) Limited
& Others [2018] provides lessons of interest to all developers
and any parties taking leases or transfers of property in reliance
on others undertaking development obligations.
The central issue was the meaning of "practical
completion" of a project in circumstances where this term was
not defined in the contracts which were in issue. This is
often the case, for example in the JCT standard forms of building
contract.
The case concerned two blocks of student accommodation in
Plymouth which were to be designed and constructed in accordance
with the relevant terms of an agreement for lease, which provided
for Mears to take a 21 year lease of the project within five days
of its practical completion. However, if practical completion
had not been achieved by a long-stop date of 11 September 2018,
then Mears could terminate the agreement for the