The Meaning Of Practical Completion Of Your Construction Project: Don't Leave It To The Contract Administrator (Or The Court) To Decide

The recent Technology and Construction Court judgment in the case of Mears Limited v Costplan Services (South East) Limited & Others [2018] provides lessons of interest to all developers ...

United KingdomReal Estate and Construction

The recent Technology and Construction Court judgment in the case of Mears Limited v Costplan Services (South East) Limited & Others [2018] provides lessons of interest to all developers and any parties taking leases or transfers of property in reliance on others undertaking development obligations.   

The central issue was the meaning of "practical completion" of a project in circumstances where this term was not defined in the contracts which were in issue. This is often the case, for example in the JCT standard forms of building contract.

The case concerned two blocks of student accommodation in Plymouth which were to be designed and constructed in accordance with the relevant terms of an agreement for lease, which provided for Mears to take a 21 year lease of the project within five days of its practical completion. However, if practical completion had not been achieved by a long-stop date of 11 September 2018, then Mears could terminate the agreement for the

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from