By Emma Colquhoun
There is much talk of a new "settlement culture" being introduced to the world of litigation by Lord Woolf’s civil justice reforms. Such is the change in attitude of the judiciary that the courts will, in future, be actively encouraging parties to compromise a claim earlier by using alternative dispute resolution procedures wherever possible. Parties will only be entitled to turn to the court system as a last resort.
It is all the more surprising therefore that there should have been two recent decisions in the Technology and Construction Court which make the early out-of-court settlement of a dispute a more risky business.
The decisions concern an everyday but tricky situation that arises in construction industry disputes. Take the following example: an employer settles a delay claim brought against him by his main contractor before trial and then tries to recover the settlement money he has paid out to the contractor by bringing a fresh action against the