The TCC in England recently considered whether a term requiring
a subcontractor to proceed regularly and diligently with their
contract works could be implied into a construction contract (Leander Construction Limited v Mulalley &
Company Limited, December 2011).
The Facts
Leander was the groundworks subcontractor at a site in Lewisham.
Mulalley, the main contractor, issued two withholding notices
meaning that no sums were due to Leander for work carried
out.
The contract itself identified a commencement date, a
subcontract period and a completion date. There were no contractual
terms regarding interim performance, milestones or sectional
completion dates.
The basis on which the notices was issued was a claim that
Leander were obliged, but failed, to carry out the sub-contract
works in accordance with the programme dates and periods set out in
the Activity Schedule. This was a subcontract document, but the
dates within it were accepted not to be