Share on LinkedInShare on LinkedIn

ARTICLE · 13 JANUARY 2012

The Ambitious Undertaking Of Implying Terms

The TCC in England recently considered whether a term requiring a subcontractor to proceed regularly and diligently with their contract works could be implied into a construction contract.

United KingdomReal Estate and Construction

The TCC in England recently considered whether a term requiring a subcontractor to proceed regularly and diligently with their contract works could be implied into a construction contract (Leander Construction Limited v Mulalley & Company Limited, December 2011).

The Facts

Leander was the groundworks subcontractor at a site in Lewisham. Mulalley, the main contractor, issued two withholding notices meaning that no sums were due to Leander for work carried out. 

The contract itself identified a commencement date, a subcontract period and a completion date. There were no contractual terms regarding interim performance, milestones or sectional completion dates. 

The basis on which the notices was issued was a claim that Leander were obliged, but failed, to carry out the sub-contract works in accordance with the programme dates and periods set out in the Activity Schedule. This was a subcontract document, but the dates within it were accepted not to be

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from