A review of Coulson J's final TCC decision in Grove, another instalment in the 'smash and grab' adjudications saga.

United KingdomReal Estate and Construction

A review of Coulson J's final TCC decision in Grove, another instalment in the 'smash and grab' adjudications saga.

This article was first published in Construction Law on 1 June 2018 (reference (2018) 29 5 Cons.Law 27).

Key Points

  • When drafting a pay less notice, an employer can refer to and rely on calculations set out in other documents. The wording of that reference, and the content referred to, must be crystal clear
  • In the absence of a pay less notice, the contractor is entitled to be paid the sum stated as due in its payment application
  • An employer who disagrees with the contractor's valuation but fails to serve the pay less notice can start a fresh adjudication to determine the true value payable but must first pay the sum stated as due