Romania And The UK: When Are The Works Taken-Over?

Fenwick Elliott LLP
Fenwick Elliott LLP
Contributor
Fenwick Elliott LLP

Fenwick Elliott LLP

Fenwick Elliott provides a comprehensive range of legal services on every aspect of the...

View firm profile
Explore more from Fenwick Elliott LLP

The issue of "taking-over" a construction project on completion in Romania always seems to raise the question of whether the works can be said to be taken-over when the contractor has complied with the contract (in terms of substantially completing the works), or whether the works need to have received the Building Permit from the local authority.

United KingdomReal Estate and Construction

Taking-Over, Completion Certificates and Building Permits

The issue of "taking-over" a construction project on completion in Romania always seems to raise the question of whether the works can be said to be taken-over when the contractor has complied with the contract (in terms of substantially completing the works), or whether the works need to have received the Building Permit from the local authority.

The circumstances in which this question arises are always the same. The contractor has, in its view, completed the works and requested taking-over. There is, no doubt, a defects or "snagging" list (assume for the moment that these items are de minimis). However, the employer's or engineer's refusal to take over is on the basis that the Building Permit has not yet been obtained. This is, apparently, required in order for the employer to know that the works are in fact complete (because they meet with the local authority's requirements) and therefore meet with the