In his final case in the Technology and Construction Court (TCC) before taking up his new position as a Court of Appeal judge, Coulson J has tipped the balance away from contractors in smash....

United KingdomReal Estate and Construction

In his final case in the Technology and Construction Court (TCC) before taking up his new position as a Court of Appeal judge, Coulson J has tipped the balance away from contractors in smash and grab adjudications.

The harsh 2011 changes to the payment terms under the Construction Act mean that employers who disagree with a contractor's valuation towards the end of the project (but who do not serve a valid pay less notice) must pay the sum stated as due in the contractor's payment application. If they do not, contractors can refer the non-payment to adjudication where they are very likely to obtain a decision in their favour ordering the employer to pay – a decision that the TCC will enforce.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.