Quietfield Ltd v Vascroft Contractors Ltd Clarifies The Status Of Adjudicators´ Decisions

In 2003, Quietfield employed Vascroft to carry out renovations to a mansion in Buckinghamshire. The contract was a standard form JCT 1998 with amendments.

United KingdomReal Estate and Construction
Shona Frame
Shona Frame
Fritha Wheeler-Ozanne
Fritha Wheeler-Ozanne
Author LinkedIn connections

The facts

In 2003, Quietfield employed Vascroft to carry out renovations to a mansion in Buckinghamshire. The contract was a standard form JCT 1998 with amendments. Vascroft applied for two extensions of time and both applications were refused. This became the subject of an Adjudication raised by Vascroft in 2005. In this Adjudication, they were unsuccessful and were not awarded either extension of time.

Later that year, and before the same adjudicator, Quietfield raised Adjudication proceedings against Vascroft claiming payment of Liquidated Damages on the basis of Vascroft's failure to complete on time and relying on the decision of the Adjudicator that Vascroft had no extension of time entitlement.