ARTICLE · 27 MAY 2021

Pay Now, Argue Later: Why It Pays To Keep On Top Of The Payment Regime

As lockdown begins to lift and we start looking forward to a future with fewer restrictions, we are reminded of the impact that the past year as had on cash flow for many in the construction industry.

United KingdomReal Estate and Construction

As lockdown begins to lift and we start looking forward to a future with fewer restrictions, we are reminded of the impact that the past year as had on cash flow for many in the construction industry. 

It is undeniable that Covid restrictions have had a tangible impact on businesses' ability to pay, yet recent court decisions indicate that the "pay now, argue later" principle adopted in relation to service of payment and/or pay less notices in construction contracts is not going away any time soon.

In Grove Developments v S&T (2018) EWCA Civ 2448, the Court of Appeal established that where a paying party has failed to serve a valid payment and/or pay less notice, while it is possible for that party to commence a "true value" adjudication to determine the value of the works claimed, it can only do so once it has complied with its statutory obligation and paid the "notified" sum (or otherwise complied with its payment obligation). While there was, at the time,

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.