ARTICLE · 12 NOVEMBER 2012

Ownership – Sub-Contractor’s Equipment – Removal Of Equipment From Site

Fenwick Elliott LLP
Fenwick Elliott LLP
Contributor
Fenwick Elliott LLP

Fenwick Elliott LLP

Fenwick Elliott provides a comprehensive range of legal services on every aspect of the...

View firm profile
Explore more from Fenwick Elliott LLP

The case of Alstom Power Ltd v Somi Implanti, [2012] EWHC 2644 (TCC), concerned an application for declaratory relief relating to the ownership of a sub-contractor’s equipment that was brought to site in connection with the construction of a power station.

United KingdomReal Estate and Construction

The case of Alstom Power Ltd v Somi Implanti, [2012] EWHC 2644 (TCC), concerned an application for declaratory relief relating to the ownership of a sub-contractor's equipment that was brought to site in connection with the construction of a power station.

The Facts

Alstom Power Limited ("Alstom") was appointed by RWE npower Plc ("RWE") as main contractor to engineer, procure and construct a substantial power plant in Pembrokeshire. Alstom retained an Italian sub-contractor, SOMI Impianti Srl ("SOMI"), to carry out various electrical and mechanical works in two work packages under the terms of a sub-contract dated 16 April 2010 ("the Sub-contract").

The Sub-contract (which was partly based on the ICE Conditions of Contract, 7th edition) included provisions that: