Today, notices and time bar provisions are found in most construction contracts. As Edward Colclough highlights, the 2016 case of Commercial Management (Investments) Ltd v Mitchell Design and Construct Ltd & Anor1 provides a useful insight into the enforceability of time bar provisions and highlights the confusion that can often exist when trying to identifying the applicable terms and conditions to a subcontract.

United KingdomReal Estate and Construction

Today, notices and time bar provisions are found in most construction contracts. As Edward Colclough highlights, the 2016 case of Commercial Management (Investments) Ltd v Mitchell Design and Construct Ltd & Anor1 provides a useful insight into the enforceability of time bar provisions and highlights the confusion that can often exist when trying to identifying the applicable terms and conditions to a subcontract.

Here, the main contractor ("Mitchell") was engaged to design and build a warehouse in Erith, Kent. Mitchell appointed a ground works subcontractor ("Regorco") to carry out certain ground treatment works, known as vibro compaction, at the site. Ten years following practical completion, the tenant of the warehouse complained of settlement of the slab beneath the warehouse production area.