Clerkenwell sought summary enforcement of an adjudicator’s decision. In Part 8 proceedings, HG sought a declaration that there was a binding agreement between the parties as a result of email correspondence on 8 February 2023, the effect of which was to revise the contractual completion dates by extending them generally by 12 weeks. The adjudicator had failed to take account of those revised dates and the decision, therefore, contained an error of law such that it should not be enforced.
The project was for the design and construction of a new 153-room hotel and 9 new-build affordable apartments. The contract was based on an amended JCT Design and Build Contract 2016. During the project, delays occurred. Following discussion, the Employer’s Agent (“EA”) emailed HG. The email said that it was an update on the “two Extensions of Time” (“EOTs”). It concluded: