In December 2016 at the FIDIC Users Conference held in London, FIDIC presented a pre-release version of its second edition of Conditions of Contracts for Plant and Design Build ("the Proposed 2017 Yellow Book") which is due to be published during the course of 2017.

United KingdomReal Estate and Construction
  1. In December 2016 at the FIDIC Users Conference held in London, FIDIC presented a pre-release version of its second edition of Conditions of Contracts for Plant and Design Build ("the Proposed 2017 Yellow Book") which is due to be published during the course of 2017.1
  2. This article addresses the changes, in relation to the Claims provisions, between the first edition of Conditions of Contracts for Plant and Design Build ("the 1999 Yellow Book") and the Proposed 2017 Yellow Book. The main changes to the Claims provisions in the Proposed 2017 Yellow Book are as follows:

2.1  The procedure for Employer and Contractor Claims is now addressed in one place under Clause 20, with both Parties being subject to the same procedure and obligations.