Building Safety: Remediation Order - Will The First-tier Tribunal Vary (Extend) The Timeframe For Compliance?

Mills & Reeve LLP
Mills & Reeve LLP
Contributor

Mills & Reeve LLP

Mills & Reeve’s staff thrive on developing great relationships and love helping clients find...

View firm profile
Explore more from Mills & Reeve LLP

The latest decision from the First-tier Tribunal (FTT) on remediation orders is about the increasingly thorny issue of seeking to vary (extend) the time for compliance with a remediation order.

United KingdomReal Estate and Construction

The latest decision from the First-tier Tribunal (FTT) on remediation orders is about the increasingly thorny issue of seeking to vary (extend) the time for compliance with a remediation order.

This decision involved Millroyd Mill in Brighouse, West Yorkshire. A remediation order was made in November 2024 which required Millroyd Island Management Co Ltd (Millroyd) to complete certain remedial works by 29 May 2026.

On 1 June 2026, Millroyd applied to the FTT seeking a 28 day stay to the remediation order “pending delivery of our final proposed programme of works to enable us to ask for the appropriate extension.”

The FTT treated this as an application to vary the remediation order, which by the way, it refused. It was critical of Millroyd stating it had failed (among other things) to:

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from